POTENTIAL PROJECT H

STALLINGS RECREATION CENTER
OWNER - CITY OF NEW ORLEANS

Project H proposes installing an underground stormwater storage tank at the Stallings Recreation Center. Once installed, the space above the tank can revert to a grassy field that can be used for sports and community programming. A similar project was built at A.L. Davis Park in Central City.

Stallings.jpg
image.png
Project X - Potential Project Sheets (9).png

POTENTIAL PROJECT H

STALLINGS RECREATION CENTER
OWNER - CITY OF NEW ORLEANS

The image with the green hexagons is from the drainage model and shows the improvements gained from implementing the potential project.  As you can see, the benefits are not restricted to the area around the project, but cascade through the drainage system as a whole.  

.568M

GALLONS OF STORMWATER STORAGE

stallings rec center.png
image.png
image.png

Give us your feedback

We’d love to hear what you thought about the potential projects.

Project Name

OUR PROJECT PARTNERS

image.png
image.png
image.png
image.png
image.png
image.png

Funding for this project is made possible through a grant by Flood Mitigation Assistance (FMA) Grant Program, managed by FEMA and administered through GOHSEP

 

Funding for the previous study was made possible with matching funds provided by National Academy of Science and Engineering Gulf of Mexico Research Program

 

The initial neighborhood study was a resident driven project led by Healthy Community Services, Water Wise Gulf South, and Bunny Friend Neighborhood Association. The data they gathered allowed them to pursue additional funding resulting in the project we are presenting today. Bringing these proposed projects to conceptual design with solid data to support them, including a Benefit Cost Analysis for each, is the next step in the implementation process.